The rule
Soil beside a footing helps carry the building. A deep trench alongside it can undermine the footing. The code's answer is an angle: draw a line sloping out and down from the bottom outside edge of the footing at 45 degrees, and keep a parallel trench outside that line.
It only applies to trenches deeper than the footing and running alongside it. A crossing trench, or one shallower than the footing bottom, isn't what this rule is about, though the inspector may still care.
If the trench has to be closer, the code lets the authority approve it under Section 301.0. That can mean an engineer's detail or shoring.
On the job
- Find the footing depth before you lay out the trench. Probe or check the plans. Guessing depth is how footings get undermined.
- If the line has to run close, talk to the inspector before you dig. An engineered detail is easier to get approved ahead of time.
- Keep any open trench near a footing shored or backfilled quickly. Section 314.4 covers backfill, and 314.3 covers trenches inside the building.
The inspector and your city's adopted edition have the final word.