Home › Code Library › CPC 1203.3

CPC 1203.3 · Fuel gas piping

Rough and final gas piping inspections

Gas piping gets a rough inspection after it's installed and before anything covers it or an appliance is hooked up, then a final piping inspection once the concealed parts are closed in. The final inspection is where the pressure test happens, and a certificate of inspection can be issued after it.

2025 California Plumbing Code, Chapter 12 (Fuel Gas Piping) · Applies to: Homes and commercial buildings

Four steps in order: rough piping inspection with the pipe exposed, covering the pipe, final piping inspection with the pressure test, and the certificate of inspection.
Rough before it's covered, final after it's closed in and before anything is attached to the piping. Diagram: Hoffman & Sons Plumbing (hoffmanandsons.com), CC BY 4.0. Free to share with credit. PNG · SVG · All diagrams

The rule

There are two gas piping inspections under the permit. The rough piping inspection comes after the piping is installed and before it's covered or concealed, and before any fixture or appliance is attached to it. The inspector checks the pipe size, the material and how it's installed.

The final piping inspection comes after the parts of the system that will be covered have been covered. It's still ahead of the fixture, appliance or shutoff valve being attached. This is the visit where the pressure test is done under Section 1213.1, using test gauges that meet Section 318.0.

If the work doesn't meet the code, the inspector tells the permit holder where it fails. When the final piping inspection finds the installation in order, the Authority Having Jurisdiction can issue a certificate of inspection under Section 1204.1.

On the job

  • Keep the pipe exposed until the rough passes. Drywall, insulation or a slab poured over uninspected gas pipe means opening it back up.
  • Bring the test rig, gauge and fittings to the final. The permit holder supplies the test apparatus, and the test is run with the inspector present.
  • Cap or plug every open outlet before the inspection so the system can hold pressure.
  • How the two visits get scheduled is up to your jurisdiction. Ask the inspector, and go with the edition and rules they've adopted.

The inspector and your city's adopted edition have the final word.