The rule
There are two gas piping inspections under the permit. The rough piping inspection comes after the piping is installed and before it's covered or concealed, and before any fixture or appliance is attached to it. The inspector checks the pipe size, the material and how it's installed.
The final piping inspection comes after the parts of the system that will be covered have been covered. It's still ahead of the fixture, appliance or shutoff valve being attached. This is the visit where the pressure test is done under Section 1213.1, using test gauges that meet Section 318.0.
If the work doesn't meet the code, the inspector tells the permit holder where it fails. When the final piping inspection finds the installation in order, the Authority Having Jurisdiction can issue a certificate of inspection under Section 1204.1.
On the job
- Keep the pipe exposed until the rough passes. Drywall, insulation or a slab poured over uninspected gas pipe means opening it back up.
- Bring the test rig, gauge and fittings to the final. The permit holder supplies the test apparatus, and the test is run with the inspector present.
- Cap or plug every open outlet before the inspection so the system can hold pressure.
- How the two visits get scheduled is up to your jurisdiction. Ask the inspector, and go with the edition and rules they've adopted.
The inspector and your city's adopted edition have the final word.