The rule
This applies to building sewers or drainage piping made of clay or other materials that aren't approved for use inside a building. That pipe can't be run in the same trench as water pipe unless three conditions are met.
The bottom of the water pipe, at points, has to be at least 12 inches above the top of the sewer or drain line. The water pipe also has to sit on a solid shelf excavated at one side of the common trench, with a clear horizontal distance of at least 12 inches from the sewer or drain line. Where a water pipe crosses over sewer or drain piping of that kind, it has to be laid at least 12 inches above it.
For this section, "within a building" means within the fixed limits of the building foundation. Table 721.1 sets other minimum distances from a building sewer, including 1 foot from an on-site domestic water service line (see Section 721.1).
On the job
- Excavate the shelf as part of the trench plan, not as an afterthought. The shelf has to be solid, not backfill.
- On a combined utility trench, check the sewer material first. If it's a material approved inside a building, this section's trench rules don't apply, but Table 721.1 distances still do.
- Mark crossings where the water service crosses the sewer lateral and keep the water at least 12 inches above the sewer.
The inspector and your city's adopted edition have the final word.