CPC 604.1.2 · Water supply and distribution

New PEX: flush, wait a week, flush again, tag the fixtures

In California housing, PEX that's the first plumbing installed in new construction gets flushed for at least 10 minutes, filled and left standing at least 1 week, then every branch flushed again. Each fixture gets a removable tag at the fill.

2025 California Plumbing Code, Chapter 6 (Water Supply and Distribution) · Applies to: Homes

Timeline of the California PEX flushing rule: first flush at least 10 minutes, fill and tag, stand at least 1 week, then flush every branch, with an example fixture tag.
First flush 10 minutes, fill and tag, stand at least 1 week, then flush every branch. Early use means running the water at least 2 minutes first. Diagram: Hoffman & Sons Plumbing (hoffmanandsons.com), CC BY 4.0. Free to share with credit. PNG · SVG · All diagrams

The rule

California's housing rules (HCD) require PEX that's the initial plumbing piping in new construction to be flushed twice over at least a week. First flush the system for at least 10 minutes. Then fill it and let it stand no less than 1 week. After the wait, flush every branch long enough to empty the volume it holds.

At the fill, each fixture gets a removable tag with the fill date, the name of whoever filled it, and the warning that if the system is used earlier than a week after the fill, the water has to run at least 2 minutes before anyone drinks or cooks with it. The tag stays on until the second flush is done. After that the owner or occupant can remove it.

It doesn't apply where PEX replaces an existing piping system of any material. Before the permit, the building official wants the contractor's written certification that the flushing will be done. The final isn't approved unless the flush and tag requirements were met, and a contractor who skips them faces penalties under the state Health and Safety Code.

On the job

  • The week starts at the fill date, so fill and tag as soon as the rough is done and tested. Waiting until the day before the final is how a schedule gets stuck.
  • Fill out the tags when you fill the system: the date and your name, one on every fixture.
  • Repiping an existing house with PEX is outside this rule, but ask the building department how it wants that permit written up.

The inspector and your city's adopted edition have the final word.