The short answer
Shower work has five numbers to know. The pan liner turns up at least 3 inches above the curb and is tested with at least 2 inches of water for at least 15 minutes (CPC 408.8). The valve limits the showerhead to 120 degrees F (CPC 408.4). The waste outlet and tailpiece are at least 2 inches (CPC 408.5). The compartment has to be at least 1024 square inches with room for a 30 inch circle, unless the receptor is at least 30 by 60 inches (CPC 408.7). Showerheads can't exceed 1.8 gpm at 80 psi (CPC 408.3).
Before the tile crew
Get the pan test and the rough-in inspection signed off before anything covers the liner, the valve body or the drain.
The pan, the liner and the water test
A site-built shower receptor has to be watertight and lined with sheet plastic, lead, copper or another durable watertight material. The lining goes up the rough side of the walls at least 3 inches above the top of the finished curb or threshold, and 3 inches above any built-in seat. It's pitched 1/4 inch per foot toward the weep holes over a smooth, solid base, then turned over the curb and fastened on the outside face. It can't be nailed or punctured less than 1 inch above the finished curb (CPC 408.8).
The drain is an approved flanged drain with a clamping ring and weep holes protected from clogging. To test it, plug the drain and fill the receptor to a depth of not less than 2 inches for not less than 15 minutes. With no curb, build a temporary 2 inch dam. The plug has to be set so both the upper and under sides of the subpan get tested at the clamp.
The valve and the 120 degree limit
Each shower or tub-shower needs its own pressure-balance, thermostatic or combination valve at the point of use, meeting ASSE 1016 or ASME A112.18.1. The water at the showerhead is limited to 120 degrees F (49 degrees C). The usual way is to set the valve's limit stop or adjust the valve per the manufacturer's instructions. A temperature-actuated flow reduction device can't stand in for the valve (CPC 408.4). Tub fillers have a similar 120 degree limit (see CPC 409.4).
Set the limit stop at rough-in and write the setting down. After the finish handle goes on, you can't tell where it is.
Drain size, curb and slope
The waste outlet and fixture tailpiece are at least 2 inches, in a drainage-approved material, with a strainer that meets ASME A112.18.2 (CPC 408.5). A curb has to be at least 1 inch lower than the sides and back of the receptor, and between 2 and 9 inches high measured from the top of the drain. The floor slopes uniformly from the sides to the drain, at least 1/8 inch and not more than 1/2 inch per foot. The nailing flange rises at least 1 inch above the receptor sides. The door opening has to give at least 22 inches of clear width (CPC 408.6).
Minimum size
The finished interior of a shower has to be at least 1024 square inches and fit a 30 inch circle, held up to 70 inches above the drain outlet. Valves, showerheads, soap dishes, shelves and grab bars can protrude. A receptor at least 30 inches wide and 60 inches long is exempt from the area and circle test, and showers designed to California accessibility rules have their own exception (CPC 408.7). When a remodel shrinks a shower, check this number before framing.
Flow and access
Showerheads and body sprays are capped at 1.8 gpm at 80 psi. If one valve feeds several outlets, the combined flow can't exceed 1.8 gpm, unless the shower is designed so only one outlet runs at a time (CPC 408.3). Concealed slip joints need an access panel at least 12 inches in the smallest dimension (CPC 402.10).
Permit and inspection
Moving or replacing shower plumbing needs a permit (CPC 104.1). Rough-in is inspected before wall or ceiling membranes go on (CPC 105.2). The inspector and your city's adopted edition of the code have the final word.
What you can safely check yourself
At home you can check the shower valve handle. It should turn from cold to hot smoothly, and the hot side shouldn't scald. If it does, call a plumber to check the limit stop. A slow drain can mean the strainer is full of hair, which you can lift out. Don't remove the valve trim or drain plug flange and don't use harsh chemicals. A damp spot on the ceiling below or a soft floor near a shower pan is a call.
Questions
How long does a shower pan test last?
At least 15 minutes with the receptor filled to at least 2 inches (CPC 408.8).
What temperature should the shower valve be limited to?
120 degrees F at the showerhead (CPC 408.4).
How big does a shower need to be?
At least 1024 square inches with room for a 30 inch circle, or a receptor at least 30 by 60 inches (CPC 408.7).
Can a shower use a smaller drain than 2 inches?
No. The waste outlet and tailpiece are at least 2 inches (CPC 408.5).
When to call
For a bathroom remodel or a new shower, call or text (760) 912-9831 before the walls are open. "Fixture installation and connections", "Rough-in plumbing" and "Final plumbing and trim-out" are on our new construction list, and "Sink & fixture installation" is on our service and repair list.