Home › Guides › ADU plumbing basics

Guide

ADU plumbing basics: permit, sewer connection, water and heater

A detached ADU is a separate structure, so it gets its own plumbing permit, and the 2025 California code adds a note that an ADU is not required to have an independent sewer connection if it meets the state ADU requirements.

The short answer

A main house and a detached ADU are separate structures, and each gets its own plumbing permit (CPC 104.1). The model code says each building gets its own connection to the public or private sewer where one is available. California adds a note that accessory dwelling units aren't required to have an independent utility drainage connection, provided they meet the state's specific ADU requirements (CPC 311.1). How the lateral is actually laid out depends on your property and the sewer agency, so confirm it with the building department before anyone digs.

Ask early

Get the sewer routing answer in writing from your building department and sewer agency. It drives trench length, cleanout placement and cost.

Separate permit, separate inspections

Each separate structure needs its own plumbing permit before work starts (CPC 104.1). The ADU's plumbing is inspected like any new work, and that includes the inspections and tests covered in our guide to new construction inspections. The inspector and your city's adopted edition of the code have the final word.

Sewer connection: own line or tie-in

Section 311.1 requires a separate and independent drainage system for each new building, with its own connection to the sewer where one is available. One exception covers a rear building on an interior lot with no sewer reaching it. The California ADU note is why an ADU may be able to tie into the main house's drain instead of getting its own lateral. Don't assume it. The answer turns on your property and the ADU rules (CPC 311.1).

A building with plumbing fixtures has to connect to a public or private sewer. A public sewer can be treated as not available only where it's more than 200 feet from the proposed building, and the building department makes that call (CPC 713.1).

If the ADU ties into the existing drain

New work has to meet the code for a new system, and the new work can't leave the existing system unsafe, insanitary or overloaded. An existing building sewer or building drain can be used for new work only if examination and test show it meets the requirements for new work (CPC 102.4). A camera scope of the existing sewer before design is how that gets answered. Piping a new bath group into an old line that can't carry it is a problem no matter how clean the new pipe is. Sewers are sized by the total fixture units they carry, and can't be smaller than the building drain (CPC 717.1).

Slope matters on both. Building drains and horizontal drains run at least 1/4 inch per foot (CPC 708.1). If the ADU sits lower than the next upstream manhole cover, its fixtures need a backwater valve (CPC 710.1).

Cleanouts and trench rules

The sewer needs a cleanout inside near the connection with the building drain, or outside at the lower end of the building drain extended to grade, and more at intervals of 100 feet or less on straight runs (CPC 719.1). A building sewer stays 2 feet from buildings and structures, 1 foot from an on-site water service line and 10 feet from a public water main, among other distances (CPC 721.1). Walk the route with the site plan before the trench is opened.

Water service and shutoff

A fullway shutoff valve goes on the discharge side of each water meter and unmetered supply, and one for each building on a premises. A single-family house and the buildings accessory to it can share one valve (CPC 606.2). Whether your ADU counts as accessory for this and how it's metered is a question for the water agency. Plan where the shutoff lives so the owner of either unit can reach it.

Water heater

A water heater install needs a permit before work, including a replacement (CPC 502.1). Storage heaters are sized by first-hour rating, based on bathrooms and bedrooms. A house with 2 to 2.5 baths and 3 bedrooms needs a rating of at least 62 gallons (CPC 501.1). A tankless unit changes the gas sizing, so check it before you pick.

What you can safely check yourself

If you're planning an ADU, locate your existing cleanouts, main water shutoff and sewer line route on the property, and keep them uncovered. Take photos. Don't dig near buried lines without calling 811 first. Don't pour anything into a cleanout. Ask your sewer agency for the manhole cover elevation near your lot.

Questions

Does my ADU need its own sewer connection?

California adds a note that ADUs aren't required to have an independent drainage connection if they meet the state's ADU requirements. Confirm how it applies to your lot (CPC 311.1).

Does a detached ADU need its own plumbing permit?

Yes. Permits go by building or structure (CPC 104.1).

Can the ADU use my existing sewer line?

Only if examination and test show it can carry the new work (CPC 102.4).

Does the ADU need a separate water shutoff?

The code puts one fullway valve per building, and a house and its accessory buildings can share one (CPC 606.2). Ask your water agency about metering.

When to call

If you're adding an ADU, garage conversion or addition, call or text (760) 912-9831 early, before the sewer routing is set. "Residential and commercial new construction, remodels and additions" are the core of our new construction work, including "Water and sewer lines" and "Water heater installation". Existing-home plumbing fixes are on our service and repair list.