Plumbing inspections on new construction: underground, rough-in and final
New plumbing work gets three inspections: underground before backfill, rough-in before walls and ceilings are covered, and final when the installation is complete. Nothing gets covered until it passes.
The short answer
The code names three inspections. Underground comes after trenches are dug and bedded and pipe is installed, before backfill. Rough-in comes before wall or ceiling membranes go on. Final comes when the installation is complete (CPC 105.2). The permit holder or authorized agent schedules each one, and the building department can ask for at least 1 working day of notice. Drain and vent get a water test or an air test, and water piping gets tested too. Anything covered before it's inspected, tested and approved has to be uncovered.
Don't cover it
Pipe in a trench, in a wall or behind a ceiling stays visible until the inspector approves it. Covering early means opening it back up.
Underground inspection
The pipe has to lie on a firm bed for its full length, with no rocks, hollows or loose fill under it (CPC 313.5). Backfill is clean earth in thin layers up to 12 inches over the pipe, then compacted to grade. Thermoplastic sewer pipe also needs a 4 inch granular bed and compaction in 6 inch layers to at least 85 percent standard Proctor density (CPC 314.4). Call for the inspection with the pipe bedded, every joint in view and the test in place. A trench that's already filled gets dug back out.
Rough-in inspection
Rough-in is the big one. It's before wall and ceiling membranes go on, so schedule it ahead of the drywall crew. The inspector checks pipe sizing, slope, venting, supports, cleanouts, closet bends cut flush with the flange (CPC 402.6), and firestopping where pipe crosses a rated wall or floor, which needs a tested system with an F rating of at least 1 hour and not less than the assembly's rating (CPC 1404.3). Pipe that sits within 1 inch of the framing face needs a steel nail plate, at least No. 18 gauge, extending at least 1-1/2 inches past the pipe (CPC 312.9).
Gas piping gets its own rough inspection before it's concealed or any appliance is attached, then a final piping inspection where the pressure test is run (CPC 1203.3).
The tests
A drain and vent water test fills the system, whole or in sections, with no section under a 10 foot head of water, and the water stays in for at least 15 minutes before the inspection begins (CPC 712.2). An air test uses a uniform 5 psi, or enough to balance 10 inches of mercury, held for at least 15 minutes with no added air, and plastic pipe can't be tested with air (CPC 712.3). Water supply piping is tested with water at working pressure or more, or with air at not less than 50 psi, for at least 15 minutes (CPC 609.4). The tests are done in the presence of the inspector, and the permit holder supplies the equipment, labor and gauges (CPC 105.3). Leave the test up until the inspector has seen it. Drain down early and you start over.
Final inspection
Final is when fixtures are set, traps are filled, and the installation is complete. The inspector can ask for a final test with water in the traps, and can require cleanouts to be removed to confirm the test reached every part of the system (CPC 712.2). When the tests and inspections show the work meets the code, the building department issues a certificate of approval on request (CPC 105.3). For PEX that is the initial piping in new housing, the final isn't approved unless the flush and tag requirements were met (CPC 604.1.2).
Permits and plan changes
Approved plans can't be changed without the building department's authorization. In California, a permit becomes invalid if work doesn't start within 12 months or is suspended or abandoned for 12 months, and the building official can grant written extensions of up to 180 days each (CPC 104.4). Keep the permit, plans and manufacturer instructions on site. No plans or no access on inspection day can draw a reinspection fee (CPC 105.2). The inspector and your city's adopted edition of the code have the final word.
What you can safely check yourself
As an owner, keep a folder with the permit, the approved plans and the signed inspection card. Leave test gauges, plugs and standing water alone until the inspector has approved. Don't have drywall, insulation or a slab closed over plumbing before its inspection. Ask your plumber to show you the signed final when the job is done.
Questions
Who schedules plumbing inspections?
The permit holder or authorized agent does (CPC 105.2). Your building department sets how requests are made.
Can the walls be closed before the inspection?
No. Work that's covered before it's inspected, tested and approved has to be uncovered (CPC 105.2).
What happens if the inspector isn't satisfied?
The permit holder makes corrections and resubmits for test or inspection (CPC 105.3).
Does a permit expire?
In California, it can lapse after 12 months of no start or 12 months of stalled work, with written extensions possible (CPC 104.4).
When to call
If you're building, adding on or remodeling and need the plumbing inspected in order, call or text (760) 912-9831. "Underground and slab plumbing", "Rough-in plumbing", "Final plumbing and trim-out" and "Code compliance and inspections" are all on our new construction list. For existing homes, see service and repair.