Underground and slab plumbing is the pipe that goes in before the concrete does: drains, the sewer connection and water lines that get inspected in the open, then buried for good. Hoffman & Sons Plumbing lists it under new construction.

What it is

Once a slab is poured or a trench is filled, that pipe is hard to reach, so this is the stage where details matter most. It covers the building drain and sewer connection, the drain and vent stubs that come up through the floor for each fixture, and any water or gas piping that has to run below grade or under the slab.

Residential and commercial jobs follow the same basic order. Everything below ground goes in first, gets inspected while it's still in view, and only then gets covered.

How the work goes on a job

  1. Read the plans and mark the layout: where each fixture lands, where the building drain leaves the structure, and where the sewer and water connections are.
  2. Dig and bed the trench. Pipe has to lie on a firm bed for its whole length (CPC 313.5), and a trench that runs beside a footing has its own rules (CPC 314.1).
  3. Set the drain pipe at a uniform slope of at least 1/4 inch per foot (CPC 708.1) and place cleanouts where the code asks for them (CPC 707.4 cleanouts).
  4. Sleeve or block out each pipe that passes through a footing or stem wall so the building can settle without loading the pipe, and keep pipe out of direct contact with concrete (CPC 312.1, CPC 312.2, CPC 312.10).
  5. Run any water piping with slab rules in mind: protective coating on ferrous pipe, and copper tube with as few joints under the slab as possible (CPC 609.3).
  6. Test the drain piping with water, or with air where the pipe material allows it (CPC 712.2, CPC 712.3).
  7. Call for the underground inspection with the pipe bedded and every joint in view (CPC 105.2).
  8. Backfill after approval: clean earth in thin layers to 12 inches above the pipe, then compact to grade (CPC 314.4). Seal the void around each pipe that comes up through the slab.

Inspections and tests the code calls for

Underground is the first of three inspections on a plumbing permit (underground, rough-in and final), and the permit holder schedules it. If the trench gets covered before the inspector arrives, expect to dig it back out. Tests happen in the inspector's presence, and a passing system earns a certificate of approval (CPC 105.3).

Pipe, fittings and fixtures also have to be listed and marked for their use (CPC 301.2), and a defect can't be patched with a sealant or a dab of cement. A bad piece gets cut out and replaced (CPC 309.2).

What you can safely check yourself

  • Look for a damp or soft strip in the yard or along the foundation, a line of settling over a buried pipe, or cracked or stained concrete where a pipe enters.
  • Check the water meter with every fixture and appliance off. If the leak indicator or dial keeps moving, water is going somewhere.
  • Know where your main water shutoff is.
  • Don't dig near a buried line, chip at concrete around a pipe, or cut into a slab. Call 811 before any digging so buried lines get marked, and call a licensed plumber about anything you see.

Who it's for

Builders and general contractors doing new homes, additions and commercial buildings, who need the underground work in and signed off before the slab. Homeowners planning an addition or a new structure on their lot are in the same position and can ask us how the underground work fits the schedule.

Where this sits on our service lists

On our New Construction list: “Underground and slab plumbing”.

Call or text

Call (760) 912-9831 or text (760) 912-9831 to talk through your project.

The inspector and the city's adopted edition have the final word on every code point on this page. The code library here summarizes the 2025 California Plumbing Code, effective at the start of 2026, in our own words.